3-16-12: Signed purchase agreement with Ryan Homes
4-16-12: Meeting with Guardian and CTI for flooring selections
4-21-12: Completed mortgage application with NVR mortgage
5-14-12: Pre-construction Meeting
5-23-12: Received initial mortgage approval (although I wasn't notified until June 1st)
7-10-12: Pre-drywall meeting
Construction Progress
6-4-12: We broke ground!
6-7-12: Foundation poured
6-8-12: Foundation walls
6-17-12: Lumber delivered
6-20-12: Framing begins for first floor
6-24-12 Framing begins on second floor
6-27-12: Roofing completed
6-28-12: Electrical and plumbing rough-ins
7-1-12: Sprinkler system
7-6-12: Electrical and Guardian wiring
7-9-12: Insulation in walls
7-15-12: Drywall
7-18-12: We have siding!
7-19-12 Painting begins
7-20-12 Cabinets installed
7-21-12: Stone!
7-27-12: Light fixtures
7-31-12: Flooring installation begins
8-1-12: Countertops installed
Settlement info
8-24-12: Pre-settlement demostration
8-27-12: Settlement day!